Rule I: Drainage Systems

1. Policy.

It is the policy of the Board of Managers to regulate new construction, improvement or repair of public or private drainage systems (open and tiled) for the following purposes:

2. Regulation.

No drainage system may be constructed, improved or repaired without first obtaining a permit from the District.

3. Criteria.

A permit applicant for construction, improvement or repair of a public or private drainage system must:

4. Required Exhibits.

The following exhibits must accompany the permit application. One set, full size; two sets, reduced to maximum size of 11”x17”.

5. Exceptions.

The Board of Managers may waive the requirement of a permit under this rule for repair to a drainage system if the applicant proposes to repair a tiled system of less than fifty feet in length, and where such repair would not alter the invert of the system.